Common Systems Group (CSG)
April 26, 2005
Meeting Summary
CSG Attendees: Paul Craft, Steve Duim, Jason Frand, Bill
Jepson, Robert Konishi, Max Kopelevich, Michelle Lew, Kathleen O’Kane, Tom
Phelan, Sean Pine, Nick Reddingius, Terry Ryan, Ruth Sabean, Marsha Smith, Eric
Splaver, Pam Taylor, Kent Wada, Esther
Woo-Benjamin, Don Worth
Guests: Carol King (Grad Division), Mike Lee (PDP
Participant), Tom Trappler (OIT)
Agenda
1)
UCLA
Policy 411: Domain Names
A second vote on a revised Policy 411 was conducted by email, with the
following results:
|
Did not Vote |
0 |
|
|
Abstain |
0 |
|
|
Not Approve |
0 |
|
|
Approve |
8 |
|
|
Approve with Caveats |
9 |
Caveats: 1.
The appeals
section is still inadequate. The appeals should be directed to the
Associate Vice Chancellor of Information Technology, who in consultation with
other campus officials, as appropriate, will make a final
determination. Having the head of the office that initially denies the
request be the arbitrator doesn’t make sense. I believe that Jim would
certainly consult with the Vice Chancellor of External Affairs regarding the
matter, but the one to make the determination must be impartial. |
|
|
|
2.
I also suggest
changing the form to solicit “reasons for denial” in the appropriate
section. The current dotted line really doesn’t imply that providing a
reason is required. |
|
|
|
3.
There needs to
be clarification of what a "clear institutional reason is" for a
campus entity to be denied its name. For example, is the use of
acronyms still a "clear institutional reason"? The proposed policy
does not clearly eliminate the possibility of arbitrariness that called it
into question in the first place. |
This vote forms the CSG’s recommendation to the ITPB on the proposed
policy update. The recommendation will include written reports on the two
positions regarding who should be the final decision maker on appeals to
requests for domain names.
Actions:
·
During
the meeting Paul Craft and Kent Wada were asked to develop position papers that
addressed the caveat of what office has final decision-making. Subsequent to
the meeting it was decided that because this constituted a change in policy
and/or interpretation of the policy the domain name policy should be taken back
to the ITPB.
2)
Payment Card Industry (PCI) Data Security
Standard
VISA and MasterCard have recently issued Payment Card Industry (PCI) security standards that all merchants must comply with by June of this year. Consequences for non-compliance can be serious. UCLA is being viewed as a single (3rd tier) entity so non-compliance by any unit within UCLA will be treated as non-compliance by UCLA. Requirements for network security are higher than UCLA’s minimum security standards. Requirements for physical security are at the data center level. AIS has proposed a central service for collecting credit card numbers and is working with the external auditors to meet their requirements. OIT is taking the lead on the IT components of this issue and will be pulling together a group to work on solutions.
There was a comment that communication from department CAO/CFOs to their IT directors does not always happen (as in this case). There was a suggestion that IT directors be copied on memos (regarding issues that might have an IT component) to CAO/CFOs.
3)
UCLA Policy 420: SB1386 (revised)
This policy has been updated to bring it into line with current
practice. All updates are based on lessons learned from the 8 incidents at UCLA
since July 2003. Kent Wada will be calling for an email vote on the revised
policy. There was agreement that when voting by email, members should be given
a minimum of 48 hours to cast their vote.
4)
UCLA Policy 401 - Minimum
Security Standards - Implementation: ITPB direction
A vote was conducted by email, with the following results:
|
Did not vote |
0 |
|
|
Abstain |
1 |
|
|
Not Approve |
0 |
|
|
Approve |
15 |
|
|
Approve with Caveats |
1 |
Caveat: I
believe that the situation of student owned computers attaching to the
network either through wireless, dial-up and/or through a departmental wired
connection should be addressed. |
The ITPB and CSG have both approved these standards in principle. The
next step is to send this draft policy to the campus for larger comment and
review. The review will likely be a 30-day period. The implementation goal is
still October 1, 2005.
5)
Policy for handling “restricted data”
There was agreement that a next step should be to develop a common
definition of data types.
6)
Network Review Next Process Steps
a.
Marsha
Smith explained the proposal to use the existing governance structure and
process to analyze and respond to the network review report. The CSG (with
involvement of other CIOs and technical staff across campus) would do a
preliminary assessment for the ITPB. The ITPB would take the lead in tasking
the existing IT committees or forming sub groups to do detailed analysis work
or campus consultation. There was agreement that this structure makes sense.
However, there was also concern that the ITPB and CITI are not representative
bodies. The ITPB does not have significant representation from Deans. (Jim
Davis will be working with the ITPB on a defined mechanism for direct
involvement of the Deans).
b. There was a general discussion about the
network review report. Following are some around the table comments and
questions:
·
Some
statements were vague (e.g. ‘adopt revolutionizing new technologies’).
·
There
were no great revelations.
·
Where is
the support for the statement that service levels are high? How do they know
this? How representative was the community that was surveyed?
·
Who are
our peers? Are we comparing apples to apples? Some are profit centers and some
are cost centers. Classifications are made regardless of funding source.
·
A lot of
issues are not network issues.
·
Build on
core strength of campus – richness of expertise.
·
How do
we have a more coordinated approach to basic infrastructure requirements while
still preserving the strong local talent? Find ways to leverage local
resources.
·
Look at
wireless process – improve efficiency of process.
·
Diffused
accountability is a problem. Need top down assessment of network for
accountability.
·
A good
starting point – (friendly) security audits, report cards, not witch hunts.
·
Need
compromises that preserve 90% of each side’s needs.
·
Need a
collective body viewing the whole campus (e.g. CSG).
·
Need to
look at services.
·
Look
across campus and identify those whose requirements aren’t being met.
·
Look at
models on campus.
c.
There
was a discussion about the draft Assessment Framework for the External Network
Review Report document.
·
There
was agreement with the ‘in scope’ and ‘out of scope’ approach.
·
There
was agreement to form a steering committee to develop a charge and action plan
to bring back to the May CSG meeting.
Actions:
·
Marsha
agreed to call a steering committee meeting within the next two weeks. Every
CSG member is welcome to attend.
·
Everyone
is asked to provide input on the draft Assessment Framework document within the
next two weeks (provide feedback on assumptions, scope, organization of
document, groups).
Meeting Schedule for
Remainder of 2005:
|
Tuesday |
May
24 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
June
28 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
July
26 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
August
23 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
September
27 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
October
25 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
November
22 |
2:00
– 4:00 p.m. |
2121
Murphy |
|
Tuesday |
December
20 |
2:00
– 4:00 p.m. |
2121
Murphy |